A process makes two products a and b and operates 5 days


A process makes two products, A and B, and operates 5 days per week, 8 hours per day. demand for the two prducts for the next week is as follows:

Day 1: A: 20 ; B: 26

Day 2: A: 10 ; B: 15

Day 3: A: 20 : B: 19

Day 4: A: 18 ; B: 20

Day 5: A: 12 ; B: 20

What is the Takt time of the process? What would a level production schedule look like?