A construction project has the following network and


Question: 1. A construction project has the following network and activity times:

a. Make a forward pass and a backward pass on the activity times.

b. Find the slack for each activity.

c. Prepare a Gantt chart for this project.

d. Activity D will be delayed by one day. What effect will this have on the project?

2286_3.png

2. A plant start-up is based on the following network

2422_Time.png

a. Draw a network for this project.

b. What is the project completion time?

c. Identify the critical path.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A construction project has the following network and
Reference No:- TGS02705225

Expected delivery within 24 Hours