A calculate the probability that the project will be


Using the following project information

Activity Optimistic Time

Estimate(weeks) Most Likely Time

Estimates (weeks) Pessimistic Time

Estimates (weeks) Immediate

Predecessor(s) Variance Expected Time

(weeks)

A 3 6 9 none 1.000 6.00B 3 5 7 A 0.444 5.00C 4 7 12 A 1.778 7.33D 4 8 10 B 1.000 7.67E 5 10 16 C 3.361 10.17F 3 4 5 D,E 0.111 4.00G 3 6 8 D,E 0.694 5.83H 5 6 10 F 0.694 6.33I 5 8 11 G 1.000 8.00J 3 3 3 H,I 0.000 3.00The critical path is A-C-E-G-I-J.

(a) Calculate the probability that the project will be completed in 38 weeks.

P(project ≤ 38) = 

(b) Calculate the probability that the project will be completed in 42 weeks.

P(project ≤ 42) = 

(Round your answers to 3 decimal places, the tolerance is +/-0.005.)