23 total 10 points based on the forecast and customer order


23. (Total 10 points) Based on the forecast and customer order information provided by the company that manufactures the external protection blocks used in the space shuttle, obtain the master production schedule (using the table below - a copy of the table is also included in the answer sheet) given the following information:

a) Initial inventory is 64 external protection blocks
b) Production will be scheduled whenever projected-on-hand drops below 10 units
c) Production lot size is 70 units.
June July 
Initial Inv. 64 1 2 3 4 5 6 7 8 
Forecast 30 30 30 30 40 40 40 40 
Customer Orders 33 20 10 4 49 10 20 62 
Projected on-hand 
MPS 

Request for Solution File

Ask an Expert for Answer!!
Operation Management: 23 total 10 points based on the forecast and customer order
Reference No:- TGS0985994

Expected delivery within 24 Hours