Needs some additional information to complete the exact


Problem 1. WeightedScore Method and Center Of Gravity Method

ABC Electronics is going to construct a new $1.2 billion semiconductor plant and has selected four towns in the Midwest as potential sites. The important location factors and ratings for each town are as follows:


Scores (0 to 100)

Location Factor

Weight

Abbeton

Bayside

Cane Creek

Dunnville

Work ethics

0.18

80

90

70

75

Quality of life

0.16

75

85

95

90

Labor laws/unionization

0.12

90

60

60

70

Infrastructure

0.10

60

50

60

70

Education

0.08

80

90

85

95

Labor skill and education

0.07

75

65

70

80

Cost of living

0.06

70

80

85

75

Taxes

0.05

65

70

55

60

Incentive package

0.05

90

95

70

80

Government regulations

0.03

40

50

65

55

Environmental regulations

0.03

65

60

70

80

Transportation

0.03

90

80

95

80

Space for expansion

0.02

90

95

90

90

Urban proximity

0.02

60

90

70

80

Recommend a site based on these location factors and ratings.

Problem 2. Excel Solver

XYZ  Furniture is one of the few remaining domestic manufacturers of wood furniture. In the current competitive environment, cost containment is the key to its continued survival. Demand for furniture follows a seasonal demand pattern with increased sales in the summer and fall months, culminating with peak demand in November.

The cost of production is $16 per unit for regular production, $24 for overtime, and $33 for subcontracting. Hiring and firing costs are $500 per worker. Inventory holding costs are $20 per unit per month. There is no beginning inventory. Ten workers are currently employed. Each worker can produce 50 pieces of furniture per month. Overtime cannot exceed regular production. Given the following demand data, use Excel Solver to design an aggregate production plan for XYZ Furniture that will meet demand at the lowest possible cost.

Input:

Beg. Wkrs

10

Regular

$16

Hiring

$500

 

 

Units/wkr

50

Overtime

$24

Firing

$500

 

 

Beg. Inv.

0

Subk

$33

Inventory

$20

 

Month

Demand

Reg

OT

Subk

Inv

#Wkrs

#Hired

#Fired

Jan

500

500

0

0

0

10

0

0

Feb

500

500

0

0

0

10

0

0

Mar

1000

1,000

0

0

0

20

10

0

Apr

1200

1,000

200

0

0

20

0

0

May

2000

1,000

1,000

0

0

20

0

0

Jun

400

400

0

0

0

8

0

12

Jul

400

400

0

0

0

8

0

0

Aug

1000

1,000

0

0

0

20

12

0

Sep

1000

1,000

0

0

0

20

0

0

Oct

1500

1,500

0

0

0

30

10

0

Nov

7000

3,500

3,500

0

0

70

40

0

Dec

500

500

0

0

0

10

0

60

Total

17,000

12,300

4,700

0

0

246

72

72
















Problem 3.

Complete the following MRP matrix for Item X. Determine when orders should be released and the size of those orders.

Item: X

LLC: 0

Period

Lot Size: Min 50

LT: 2

1

2

3

4

5

6

7

8

Gross Requirements

 

25

30

56

25

100

40

30

20

Scheduled Receipts

 

 

50

 

 

 

 

 

 

Projected on Hand

30

 

 

 

 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

Planned Order Receipts

 

 

 

 

 

 

 

 

 

Planned Order Releases

 

 

 

 

 

 

 

 

 

Release orders in periods 1 through 5 for quantities of 50, 50, 56, 50, and 50 respectively.

Problem 4.

 

XYZ Incorporated makes products from rough tree fibers. Its product line consists of five items processed through one of five machines. The machines are not identical, and some products are better suited to some machines. Given the following production time in minutes per unit, determine an optimal assignment of product to machine:

 

Machine

Product

A

B

C

D

E

1

17

10

15

16

20

2

12

 9

16

 9

14

3

11

16

14

15

12

4

14

10

10

18

17

5

13

12

 9

15

11

Problem 5- Needs some additional information to complete. The exact problem statement is  "The following probabilistic activity time estimates are for a CPM/PERT network.

Problem 5.


Time Estimates (days)

 

Time Estimates (days)

Activity

a

m

b

Activity

a

m

b

1

1

2

 6

 7

1

1.5

2

2

1

3

 5

 8

1

3

5

3

3

5

10

 9

1

1

5

4

3

6

14

10

2

4

9

5

2

4

 9

11

1

2

3

6

2

3

 7

12

1

1

1

Determine the following:

a. Expected activity times

b. Earliest start and finish times

c. Latest start and finish times

d. Activity Slack

e. Critical Path

Expected Project duration and standard deviation.

2350_CPMPERT diagram.png

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Needs some additional information to complete the exact
Reference No:- TGS0979282

Expected delivery within 24 Hours